Canada Spends Logo

Explore our Budget 2026 analysis

Grant: Discovery Grants Program - Individual

École Polytechnique de Montréal

$50,000.00

Experimental, numerical, and analytical investigations of the hydrogeotechnical behavior of paste backfill and hydraulic backfill in interaction with waste rock to approach optimal design of waste rock barricades

FY 2024-25

Summary
Backfill has become an integral part of almost all modern underground mines worldwide. Hydraulic backfill (HB) and paste backfill (PB) in form of slurry are the two most used to fill mine stopes (voids created after ore extraction). Construction of barricades at the base of stopes is necessary to retain backfill in the stopes. A critical concern for successful backfill is the stability of barricades. Traditionally, barricades are built with wood, bricks, concrete, or steel grid with shotcrete. Their construction is long and expensive. In Canada, waste rock barricades (WRB) are increasingly used. Construction of WRB is simple, fast and economic. Underground produced waste rock (WR) as the required building material can be obtained at almost zero cost. Transportation and hoisting of underground produced WR from underground to ground surface are avoided, resulting in significant reduction of energy consumption, operation costs, and greenhouse gas emissions. Despite the numerous advantages of WRB, solutions used for WRB design are far from optimal. All the analytical solutions were developed by considering iso-geostatic pressure, which is only valid for uncemented PB of low solids content instantaneously poured in base-undrained stopes. Application of these solutions results in overly conservative design of WRB. Over the years, a number of articles were published on backfill pressure by considering drainage and consolidation as well as cementation and hydration of cemented backfill. All these studies were conducted by considering base-undrained stopes or base free-draining condition for PB. The effect of drainage (compared to base-undrained stopes) or draining resistance (compared to base free-draining condition) of WRB and the effect of solids content of backfill on backfill pressure have never been considered. In addition, there is neither solution for backfill pressure estimation of HB retained by WRB nor solution for sizing WRB to retain HB. New analytical solutions are necessary for estimating the pressures of PB and HB retained by WRB. New analytical solutions are also necessary for sizing WRB to retain HB. Moreover, there is no valid method to obtain the hydrogeotechnical properties of field WR due to its excessively large particles. To fill some of the identified gaps, the effects of the solids content, binder content, and filling rate of backfill and the effect of WRB on backfill pressure of HB and PB will be studied. The stability of WRB with or without shotcrete constructed to retain either PB or HB will also be analyzed. Development of a method allowing obtaining the hydrogeotechnical properties of field WR is the applicant new axis of research under development. Realization of the program allows mining practitioners-engineers to gain a tool for making more economic and more reliable design of WRB. This helps mining industry of Canada to increase the competitiveness, maintain a high level of safety, and ensure a sustainable development.
Program
Discovery Grants Program - Individual
Location
Quebec, Canada
Recipient Type
Academia
Type
Grant
Source
NSERC's Awards Data

As published

Application id
RGPIN-2024-06859
Name nom
Li, Li
Department département
Department of Civil, Geological and Mining Engineering
Organization id
64
Institution établissement
École Polytechnique de Montréal
Province en
Québec
Province fr
Québec
Country en
CANADA
Country fr
CANADA
Fiscal year exercice financier
2024
Competition year année de concours
2024
Award amount
50000
Program id
RGPIN
Program name en
Discovery Grants Program - Individual
Program name fr
Programme de subventions à la découverte - individuelles
Group en
DISCOVERY RESEARCH
Group fr
RECHERCHE AXÉE SUR LA DÉCOUVERTE
Committee code
1509
Committee name en
Civil, Industrial and Systems Engineering
Committee name fr
Génie civil, industriel et des systèmes
Area of application code
202
Area of application group en
Natural resources (economic aspects)
Area of application group fr
Ressources naturelles (aspects économiques)
Area of application en
Mineral resources ( prospecting, exploration, mining, extraction, processing)
Area of application fr
Ressources minérales (prospection, exploration, mines, extraction et préparation)
Research subject code
1401
Research subject group en
Mining and mineral processing
Research subject group fr
Génie minier et minéral
Research subject en
Mining engineering
Research subject fr
Génie minier
Field of research list names en
Not available
Field of research list names fr
Non disponible
Socioeconomic objective list names en
Not available
Socioeconomic objective list names fr
Non disponible
Application title
Experimental, numerical, and analytical investigations of the hydrogeotechnical behavior of paste backfill and hydraulic backfill in interaction with waste rock to approach optimal design of waste rock barricades
Keywords
waste rock barricades (wrb); paste backfill; hydraulic backfill; pressure and stresses; effect of binder content on backfill pressure; effect of solid content on backfill pressure; effect of filling rate on backfill pressure; effect of wrb on backfill pressure; effect of shotcrete sprayed over downstream slope of wrb; optimal design of wrb
Application summary
Backfill has become an integral part of almost all modern underground mines worldwide. Hydraulic backfill (HB) and paste backfill (PB) in form of slurry are the two most used to fill mine stopes (voids created after ore extraction). Construction of barricades at the base of stopes is necessary to retain backfill in the stopes. A critical concern for successful backfill is the stability of barricades. Traditionally, barricades are built with wood, bricks, concrete, or steel grid with shotcrete. Their construction is long and expensive. In Canada, waste rock barricades (WRB) are increasingly used. Construction of WRB is simple, fast and economic. Underground produced waste rock (WR) as the required building material can be obtained at almost zero cost. Transportation and hoisting of underground produced WR from underground to ground surface are avoided, resulting in significant reduction of energy consumption, operation costs, and greenhouse gas emissions. Despite the numerous advantages of WRB, solutions used for WRB design are far from optimal. All the analytical solutions were developed by considering iso-geostatic pressure, which is only valid for uncemented PB of low solids content instantaneously poured in base-undrained stopes. Application of these solutions results in overly conservative design of WRB. Over the years, a number of articles were published on backfill pressure by considering drainage and consolidation as well as cementation and hydration of cemented backfill. All these studies were conducted by considering base-undrained stopes or base free-draining condition for PB. The effect of drainage (compared to base-undrained stopes) or draining resistance (compared to base free-draining condition) of WRB and the effect of solids content of backfill on backfill pressure have never been considered. In addition, there is neither solution for backfill pressure estimation of HB retained by WRB nor solution for sizing WRB to retain HB. New analytical solutions are necessary for estimating the pressures of PB and HB retained by WRB. New analytical solutions are also necessary for sizing WRB to retain HB. Moreover, there is no valid method to obtain the hydrogeotechnical properties of field WR due to its excessively large particles. To fill some of the identified gaps, the effects of the solids content, binder content, and filling rate of backfill and the effect of WRB on backfill pressure of HB and PB will be studied. The stability of WRB with or without shotcrete constructed to retain either PB or HB will also be analyzed. Development of a method allowing obtaining the hydrogeotechnical properties of field WR is the applicant new axis of research under development. Realization of the program allows mining practitioners-engineers to gain a tool for making more economic and more reliable design of WRB. This helps mining industry of Canada to increase the competitiveness, maintain a high level of safety, and ensure a sustainable development.