Grant: Engage Grants Program
University of Toronto
$24,994.00
Dynamic adjustment to regulating reserve requirements on the IESO-controlled grid
FY 2011-12
Summary
The Ontario government has used a variety of policies over the past decade, most recently the Feed-In Tariff
(FIT), to incentivise the development of renewable generation in the province. This latest policy instrument has
been well-received by investors, resulting in over 17 GW of renewable generation proposals. From these
applications, over 3,000 MW of new generation contracts have already been executed, with the majority of the
capacity based on variable generation technologies, specifically solar photovoltaic (1,021 MW) and wind
(1,815 MW) power.
While the FIT has clearly been successful in attracting renewable investment to Ontario, there are significant
operational challenges that must be addressed to ensure that the reliability of electricity supply does not suffer.
Unlike more traditional generators, such as coal and nuclear power plants, the potential output of solar and
wind power plants shifts constantly throughout the day and is difficult to predict. Because the electrical system
requires there to be a balance of supply and demand at all times, any time there is a fluctuation in solar or wind
power output there must be an opposing change in the generation or demand on the system.
Because the errors in wind forecasts and load forecasts are generally uncorrelated, the regulation requirements
are likely to change significantly from the +/- 100 MW, 50 MW/min static requirements currently in use in the
Ontario electrical system. Using static requirements that are insensitive to changing grid conditions is neither
efficient nor reliable, and so this project will focus on developing a computational method to dynamically
determine the volume and rate of regulating reserves needed to handle the influx of variable generation on the
IESO system.
Program
Engage Grants Program
Recipient
Location
Ontario, Canada
Recipient Type
Academia
Type
Grant
Source
NSERC's Awards Data
As published
Application id
418139-2011
Name nom
Tate, Joseph
Department département
Electrical and Computer Engineering, Edward S. Rogers Sr. Department of
Organization id
31
Institution établissement
University of Toronto
Province en
Ontario
Province fr
Ontario
Country en
CANADA
Country fr
CANADA
Fiscal year exercice financier
2011
Competition year année de concours
2011
Award amount
24994
Program id
EGP
Program nane en
Engage Grants Program
Program name fr
Programme de subventions d'engagement partenariat
Group en
Research partnerships programs
Group fr
Programmes de partenariat
Committee code
1553
Committee name en
Ontario Internal Decision Committee
Committee name fr
Comité de décision interne pour l'Ontario
Area of application code
304
Area of application group en
Energy resources
Area of application group fr
Ressources d'énergie
Area of application en
Electrical energy
Area of application fr
Énergie électrique
Research subject code
2501
Research subject group en
Electrical and electronic engineering
Research subject group fr
Génie électrique et électronique
Research subject en
Power systems
Research subject fr
Réseaux électriques
Partie
1
Nb partie
1
Application title
Dynamic adjustment to regulating reserve requirements on the IESO-controlled grid
Keyword
NSERC
Application summary
The Ontario government has used a variety of policies over the past decade, most recently the Feed-In Tariff
(FIT), to incentivise the development of renewable generation in the province. This latest policy instrument has
been well-received by investors, resulting in over 17 GW of renewable generation proposals. From these
applications, over 3,000 MW of new generation contracts have already been executed, with the majority of the
capacity based on variable generation technologies, specifically solar photovoltaic (1,021 MW) and wind
(1,815 MW) power.
While the FIT has clearly been successful in attracting renewable investment to Ontario, there are significant
operational challenges that must be addressed to ensure that the reliability of electricity supply does not suffer.
Unlike more traditional generators, such as coal and nuclear power plants, the potential output of solar and
wind power plants shifts constantly throughout the day and is difficult to predict. Because the electrical system
requires there to be a balance of supply and demand at all times, any time there is a fluctuation in solar or wind
power output there must be an opposing change in the generation or demand on the system.
Because the errors in wind forecasts and load forecasts are generally uncorrelated, the regulation requirements
are likely to change significantly from the +/- 100 MW, 50 MW/min static requirements currently in use in the
Ontario electrical system. Using static requirements that are insensitive to changing grid conditions is neither
efficient nor reliable, and so this project will focus on developing a computational method to dynamically
determine the volume and rate of regulating reserves needed to handle the influx of variable generation on the
IESO system.