Maritime Equipment Acquisition

Program code
BUR01 (ND)
Core responsibility
Procurement of Capabilities
In Departmental Plans
2018-19 – 2026-27 · New since an earlier plan

What it does

The Maritime Equipment Acquisition program acquires through the definition and implementation of approved capital equipment projects, new or modernized equipment required by the Canadian Armed Forces in response to evolving Defence requirements.

Source: the department's Program Inventory, via GC InfoBase.

History and lineage

First appears in GC InfoBase's actual spending by program in 2018-19. The data does not record when a program was created; it may be older than its first appearance here, which is limited by the sources (program spending starts in 2010-11, Departmental Plans in 2018-19).

2018-192019-202020-212021-222022-232023-242024-252025-262026-272027-282028-29Maritime Equipment Acquisition 2018-19: $1.18BMaritime Equipment Acquisition 2019-20: $1.24BMaritime Equipment Acquisition 2020-21: $1.95BMaritime Equipment Acquisition 2021-22: $1.89BMaritime Equipment Acquisition 2022-23: $2.04BMaritime Equipment Acquisition 2023-24: $2.3BMaritime Equipment Acquisition 2024-25: $2.84BMaritime Equipment Acquisition 2025-26: $2.52BMaritime Equipment Acquisition 2026-27: $3.81BMaritime Equipment Acquisition 2027-28: $5.48BMaritime Equipment Acquisition 2028-29: $5.34BMaritime Equipment Acquisition
Bars: spending by fiscal year (dark: actual; light: actual restated on the 2017-18 program structure; outlined: the latest plan's forecast; grey: related programs). Bands: each program in the lineage over the years it has data.
ProgramRelationYears with dataActual spending over those years
Maritime Equipment AcquisitionThis program2018-19 – 2028-29$13.4B

No earlier or later program in the same department has a similar name.

Significant changes in scope and budget

Detected from the data: renames between plans, programs it appears to replace, merge with or split into (matched by name), year-over-year changes in spending of at least 25% and $5M, or in employees of at least 20% and 25 FTEs, linked budget measures, and results indicators added or dropped.

YearWhat changedSource
2020-21Spending $1.95B, against $1.24B in 2019-20 (+57%).Actual spending (GC InfoBase)
2022-23Employees (FTEs) 451, against 373 in 2021-22 (+21%).FTEs (GC InfoBase)
2022-23Indicators added: % of Maritime capital equipment projects that remain in approved scope; % of Maritime capital equipment projects that remain on most recent approved scheduleDepartmental Results Framework (GC InfoBase)
2026-27Planned employees (FTEs) 554, against 456 in 2025-26 (+21%).FTEs (GC InfoBase)
2026-27Planned spending $3.81B, against $2.52B in 2025-26 (+51%).Latest Departmental Plan
2027-28Planned spending $5.48B, against $3.81B in 2026-27 (+44%).Latest Departmental Plan

Success criteria

The program's indicators from its department's Departmental Results Framework: the target set in each year's plan, and the result reported the following year. Source: GC InfoBase.

Historical: targets against results

% of Maritime capital equipment projects that remain in approved scope
Expected result: Maritime equipment projects remain in approved scope, schedule and expenditure authority
100%2022-23✓ met100%2023-24✓ met97%2024-25✓ met

Bars: result reported. Dashed line: target.

Report yearTargetDueResultStatus
2022-23≥ 100%2023100%Met
2023-24≥ 100%2024100%Met
2024-25≥ 90%202597%Met
% of Maritime capital equipment projects that remain on most recent approved schedule
Expected result: Maritime equipment projects remain in approved scope, schedule and expenditure authority
75%2022-23✗ not met75%2023-24✗ not met50%2024-25✗ not met

Bars: result reported. Dashed line: target.

Report yearTargetDueResultStatus
2022-23≥ 100%202375%
The Victoria Class Modernization project experienced schedule delays due to a shift of the estimated Implementation date for the Galley Improvement Project. This delay does not currently impact the timeline to achieve Initial Operational Capability.
Not met
2023-24≥ 100%202475%
The target was not achieved due to challenges encountered in the Victoria-Class Modernization (VCM) project. The estimated Project Approval for Implementation for the Flank Array Modernization and Periscope Modernization Projects has been delayed. However, this delay does not currently affect the Initial Operational Capability, and there may be opportunities to recover the schedule during the app…
Not met
2024-25≥ 90%202550%
The target was not met due to changes in project scope, limited labour availability, and unexpected production delays. These factors contributed to lower adherence to the approved schedule.
Not met
% of Maritime capital equipment projects that remain within the most recent approved expenditure authority
Expected result: Maritime equipment projects remain in approved scope, schedule and expenditure authority
77.8%2018-19✗ not met100%2019-20✓ met100%2020-21✓ met87.5%2021-22✗ not met75%2022-23✗ not met75%2023-24✗ not met66%2024-25✗ not met

Bars: result reported. Dashed line: target.

Report yearTargetDueResultStatus
2018-19≥ 100%201977.8%
The 3 most complex Major Maritime Capital Equipment projects remained in approved scope and expenditure authority. However, project schedules for maritime projects are highly dependent upon the progress of the National Shipbuilding Strategy, and as such, 2 out of the 3 projects have a 10%-20% slippage in schedule.
Not met
2019-20≥ 100%2020100%
An error in data transfer produced an inaccurate formula of record. The formula for this indicator should be “(# of Major Capital Projects with Scope Status GREEN or YELLOW / Total # of Major Capital Projects) *100".
Met
2020-21≥ 100%2021100%Met
2021-22≥ 100%202287.5%
While construction of the Joint Support Ships at the Vancouver Shipyard continued in FY 2021-22, several positive cases of COVID-19 occurred in the shipyard. The COVID-19 pandemic has impacted the project’s schedule and budget, due to effects on the supply chain and production efficiency. Requirements for self-isolation and travel restrictions have added challenges for some suppliers as well as p…
Not met
2022-23≥ 100%202375%
While construction of both Joint Support Ships (JSS) continues to progress, the project has faced challenges as a result of the COVID-19 pandemic, as well as those related to building a first-of-class ship. Budget risk remains red given the current forecast for spending, which indicates the project will exceed Expenditure Authority including approved contingency funds.
Not met
2023-24≥ 100%202475%
Target was not met due to challenges encountered with the Joint Support Ship (JSS) project. Although construction of both JSS vessels is ongoing, the project has been affected by difficulties related to the COVID-19 pandemic and the complexities of building a first-of-class ship.
Not met
2024-25≥ 90%202566%
The target was not met due to ongoing budgetary pressures and schedule risks across key maritime projects. One third of Maritime Equipment Program projects are expected to use over 50% of approved contingency funds. High-cost projects such as The River Class Destroyer project and the Joint Support Ship Project are undergoing further assessment due to project scope, schedule changes, and changes i…
Not met

Current: the 2026-27 plan's targets

% of Maritime capital equipment projects that remain in approved scope
Expected result: Maritime equipment projects remain in approved scope, schedule and expenditure authority
90%2026-27

Bars: result reported. Dashed line: target.

Report yearTargetDueResultStatus
2026-27≥ 90%2027—Planned
% of Maritime capital equipment projects that remain on most recent approved schedule
Expected result: Maritime equipment projects remain in approved scope, schedule and expenditure authority
90%2026-27

Bars: result reported. Dashed line: target.

Report yearTargetDueResultStatus
2026-27≥ 90%2027—Planned
% of Maritime capital equipment projects that remain within the most recent approved expenditure authority
Expected result: Maritime equipment projects remain in approved scope, schedule and expenditure authority
90%2026-27

Bars: result reported. Dashed line: target.

Report yearTargetDueResultStatus
2026-27≥ 90%2027—Planned

Future goals: targets due after 2026-27

No targets with a later due date.

Spending and employees: planned against actual

Spending

2018-19: $609M2018-19: $1.18B2018-192019-20: $1.08B2019-20: $1.24B2019-202020-21: $1.51B2020-21: $1.95B2020-212021-22: $2.12B2021-22: $1.89B2021-222022-23: $2.71B2022-23: $2.04B2022-232023-24: $2.55B2023-24: $2.3B2023-242024-25: $2.53B2024-25: $2.84B2024-252025-26: $2.52B2025-262026-27: $3.81B2026-272027-28: $5.48B2027-282028-29: $5.34B2028-29
Outlined bar: planned in that year's Departmental Plan (dashed: the latest plan, for years not yet reported). Filled bar: actual.
Show the numbers
Fiscal yearPlannedActual
2018-19$609M$1.18B
2019-20$1.08B$1.24B
2020-21$1.51B$1.95B
2021-22$2.12B$1.89B
2022-23$2.71B$2.04B
2023-24$2.55B$2.3B
2024-25$2.53B$2.84B
2025-26$2.52B—
2026-27$3.81B—
2027-28$5.48B*—
2028-29$5.34B*—

Employees (FTEs)

2018-19: 3732018-19: 4122018-192019-20: 4282019-20: 3632019-202020-21: 3822020-21: 3722020-212021-22: 4662021-22: 3732021-222022-23: 3732022-23: 4512022-232023-24: 4042023-24: 4932023-242024-25: 4282024-25: 5252024-252025-26: 4562025-262026-27: 5542026-272027-28: 5592027-282028-29: 5632028-29
Outlined bar: planned in that year's Departmental Plan (dashed: the latest plan, for years not yet reported). Filled bar: actual.
Show the numbers
Fiscal yearPlannedActual
2018-19373412
2019-20428363
2020-21382372
2021-22466373
2022-23373451
2023-24404493
2024-25428525
2025-26456—
2026-27554—
2027-28559*—
2028-29563*—

Planned spending, plan by plan

Each row is one year's Departmental Plan and its forecast for the next three fiscal years; read a column down to see how the forecast for one year changed. The last row is what was actually spent. Click an amount for its source. Biggest changes in federal spending plans

Actual spending is from Departmental Results Reports and the Public Accounts, as published in GC InfoBase. FTEs are full-time equivalents.