Aerospace Equipment Acquisition

Program code
BUR03 (ND)
Core responsibility
Procurement of Capabilities
In Departmental Plans
2018-19 – 2026-27 · New since an earlier plan

What it does

The Aerospace Equipment Acquisition program acquires through the definition and implementation of approved capital equipment projects, new or modernized equipment required by the Canadian Armed Forces in response to evolving Defence requirements.

Source: the department's Program Inventory, via GC InfoBase.

History and lineage

First appears in GC InfoBase's actual spending by program in 2018-19. The data does not record when a program was created; it may be older than its first appearance here, which is limited by the sources (program spending starts in 2010-11, Departmental Plans in 2018-19).

2018-192019-202020-212021-222022-232023-242024-252025-262026-272027-282028-29Aerospace Equipment Acquisition 2018-19: $743MAerospace Equipment Acquisition 2019-20: $809MAerospace Equipment Acquisition 2020-21: $1.08BAerospace Equipment Acquisition 2021-22: $846MAerospace Equipment Acquisition 2022-23: $945MAerospace Equipment Acquisition 2023-24: $1.73BAerospace Equipment Acquisition 2024-25: $3.26BAerospace Equipment Acquisition 2025-26: $5.55BAerospace Equipment Acquisition 2026-27: $7.1BAerospace Equipment Acquisition 2027-28: $9.93BAerospace Equipment Acquisition 2028-29: $7.93BAerospace Equipment AcquisitionAerospace Acq…Aerospace Equipment Acquisition
Bars: spending by fiscal year (dark: actual; light: actual restated on the 2017-18 program structure; outlined: the latest plan's forecast; grey: related programs). Bands: each program in the lineage over the years it has data. The line at the bottom shows this program's names over time.
ProgramRelationYears with dataActual spending over those years
Aerospace Equipment AcquisitionThis program2018-19 – 2028-29$9.41B

No earlier or later program in the same department has a similar name.

Significant changes in scope and budget

Detected from the data: renames between plans, programs it appears to replace, merge with or split into (matched by name), year-over-year changes in spending of at least 25% and $5M, or in employees of at least 20% and 25 FTEs, linked budget measures, and results indicators added or dropped.

YearWhat changedSource
2019-20Renamed from “Aerospace Acquisition” to “Aerospace Equipment Acquisition”.GC InfoBase program names by year
2020-21Spending $1.08B, against $809M in 2019-20 (+33%).Actual spending (GC InfoBase)
2022-23Employees (FTEs) 467, against 287 in 2021-22 (+63%).FTEs (GC InfoBase)
2022-23Indicators added: % of Aerospace capital equipment projects that remain in approved scope; % of Aerospace capital equipment projects that remain on the most recent approved scheduleDepartmental Results Framework (GC InfoBase)
2023-24Employees (FTEs) 322, against 467 in 2022-23 (−31%).FTEs (GC InfoBase)
2023-24Indicators added: % of Aerospace capital equipment projects that remain within the most recent approved expenditure authority as forecasted for the fiscal yearDepartmental Results Framework (GC InfoBase)
2023-24Indicators dropped: % of Aerospace capital equipment projects that remain on the most recent approved scheduleDepartmental Results Framework (GC InfoBase)
2023-24Spending $1.73B, against $945M in 2022-23 (+83%).Actual spending (GC InfoBase)
2024-25Employees (FTEs) 413, against 322 in 2023-24 (+28%).FTEs (GC InfoBase)
2024-25Indicators added: % of Aerospace capital equipment projects that remain within approved scheduleDepartmental Results Framework (GC InfoBase)
2024-25Indicators dropped: % of Aerospace capital equipment projects that remain within the most recent approved expenditure authority as forecasted for the fiscal yearDepartmental Results Framework (GC InfoBase)
2024-25Spending $3.26B, against $1.73B in 2023-24 (+89%).Actual spending (GC InfoBase)
2025-26Planned spending $5.55B, against $3.26B in 2024-25 (+70%).Latest Departmental Plan
2026-27Planned employees (FTEs) 488, against 393 in 2025-26 (+24%).FTEs (GC InfoBase)
2026-27Indicators added: % of Aerospace capital equipment projects that remain on the most recent approved scheduleDepartmental Results Framework (GC InfoBase)
2026-27Indicators dropped: % of Aerospace capital equipment projects that remain within approved scheduleDepartmental Results Framework (GC InfoBase)
2026-27Planned spending $7.1B, against $5.55B in 2025-26 (+28%).Latest Departmental Plan
2027-28Planned spending $9.93B, against $7.1B in 2026-27 (+40%).Latest Departmental Plan

Success criteria

The program's indicators from its department's Departmental Results Framework: the target set in each year's plan, and the result reported the following year. Source: GC InfoBase.

Historical: targets against results

% of Aerospace capital equipment projects that remain in approved scope
Expected result: Aerospace capital equipment projects remain in approved scope, schedule and expenditure authority
89%2022-23✗ not met100%2023-24✓ met92%2024-25✓ met

Bars: result reported. Dashed line: target.

Report yearTargetDueResultStatus
2022-23≥ 100%202389%
Existing schedule and budgetary limits are insufficient to deliver the scope of the Maritime Helicopter Project (MHP).
Not met
2023-24≥ 100%2024100%Met
2024-25≥ 90%202592%Met
% of Aerospace capital equipment projects that remain on the most recent approved schedule
Expected result: Aerospace capital equipment projects remain in approved scope, schedule and expenditure authority
89%2022-23✗ not met

Bars: result reported. Dashed line: target.

Report yearTargetDueResultStatus
2022-23≥ 100%202389%
Time required to complete remaining work for MHP capability delivery will result in delay to the Final Operational Capability until 2026.
Not met
% of Aerospace capital equipment projects that remain within the most recent approved expenditure authority
Expected result: Aerospace capital equipment projects remain in approved scope, schedule and expenditure authority
95.8%2018-19✗ not met100%2019-20✓ met88.9%2020-21✗ not met92.6%2021-22✗ not met89%2022-23✗ not met100%2023-24✓ met81%2024-25✗ not met

Bars: result reported. Dashed line: target.

Report yearTargetDueResultStatus
2018-19≥ 100%201995.8%
The Future Fighter Capability Project is managing a number of risks which have the potential to impact the schedule. Mitigation strategies are in place.
Not met
2019-20≥ 100%2020100%
An error in data transfer produced an inaccurate formula of record. The formula for this indicator should be “(# of Major Capital Projects with Scope Status GREEN or YELLOW / Total # of Major Capital Projects) *100".
Met
2020-21≥ 100%202188.9%
Extended work periods affected the availability of a fleet.
Not met
2021-22≥ 100%202292.6%
Interim Fighter Capability Project – The performance result was impacted by significant cost pressures associated with infrastructure activities due to elevated construction costs in the Ottawa area, as well as higher than anticipated aircraft related costs. All efficiencies with respect to equipment and infrastructure scope have been explored and implemented, scope has been reduced to remain wit…
Not met
2022-23≥ 100%202389%
Remaining work required for MHP capability delivery will require funding beyond current budgetary limits.
Not met
2023-24≥ 100%2024100%Met
2024-25≥ 90%202581%
The target was not met as several projects required the release of all contingency funding to achieve the approved scope (CF-188 Hornet Advanced Multi-Role Infrared Sensor, Tactical Control Radar, Interim Fighter Capability, GPS Advanced Navigation). Defence industry inflationary pressure was a common theme.
Not met
% of Aerospace capital equipment projects that remain within approved schedule
Expected result: Aerospace capital equipment projects remain in approved scope, schedule and expenditure authority
62%2024-25✗ not met

Bars: result reported. Dashed line: target.

Report yearTargetDueResultStatus
2024-25≥ 90%202562%
The target was not met due to several factors causing delays including: technical challenges delaying design finalization; contractor capacity; and, resource conflicts with in-service sustainment priorities. In addition, Full Operational Capability was delayed for the Aurora Incremental Modernization, Tactical Control Radar, Hornet Extension, Interim Fighter Capability, and CT-114 Tutor Extension.
Not met
% of Aerospace capital equipment projects that remain within the most recent approved expenditure authority as forecasted for the fiscal year
Expected result: Aerospace capital equipment projects remain in approved scope, schedule and expenditure authority
100%2023-24✓ met

Bars: result reported. Dashed line: target.

Report yearTargetDueResultStatus
2023-24≥ 100%2024100%Met

Current: the 2026-27 plan's targets

% of Aerospace capital equipment projects that remain in approved scope
Expected result: Aerospace capital equipment projects remain in approved scope, schedule and expenditure authority
90%2026-27

Bars: result reported. Dashed line: target.

Report yearTargetDueResultStatus
2026-27≥ 90%2027—Planned
% of Aerospace capital equipment projects that remain on the most recent approved schedule
Expected result: Aerospace capital equipment projects remain in approved scope, schedule and expenditure authority
90%2026-27

Bars: result reported. Dashed line: target.

Report yearTargetDueResultStatus
2026-27≥ 90%2027—Planned
% of Aerospace capital equipment projects that remain within the most recent approved expenditure authority
Expected result: Aerospace capital equipment projects remain in approved scope, schedule and expenditure authority
90%2026-27

Bars: result reported. Dashed line: target.

Report yearTargetDueResultStatus
2026-27≥ 90%2027—Planned

Future goals: targets due after 2026-27

No targets with a later due date.

Spending and employees: planned against actual

Spending

2018-19: $1.03B2018-19: $743M2018-192019-20: $814M2019-20: $809M2019-202020-21: $1.08B2020-21: $1.08B2020-212021-22: $1.16B2021-22: $846M2021-222022-23: $769M2022-23: $945M2022-232023-24: $1.08B2023-24: $1.73B2023-242024-25: $2.57B2024-25: $3.26B2024-252025-26: $5.55B2025-262026-27: $7.1B2026-272027-28: $9.93B2027-282028-29: $7.93B2028-29
Outlined bar: planned in that year's Departmental Plan (dashed: the latest plan, for years not yet reported). Filled bar: actual.
Show the numbers
Fiscal yearPlannedActual
2018-19$1.03B$743M
2019-20$814M$809M
2020-21$1.08B$1.08B
2021-22$1.16B$846M
2022-23$769M$945M
2023-24$1.08B$1.73B
2024-25$2.57B$3.26B
2025-26$5.55B—
2026-27$7.1B—
2027-28$9.93B*—
2028-29$7.93B*—

Employees (FTEs)

2018-19: 2292018-19: 2522018-192019-20: 2762019-20: 2382019-202020-21: 3462020-21: 2822020-212021-22: 3212021-22: 2872021-222022-23: 2822022-23: 4672022-232023-24: 2902023-24: 3222023-242024-25: 3082024-25: 4132024-252025-26: 3932025-262026-27: 4882026-272027-28: 4892027-282028-29: 4852028-29
Outlined bar: planned in that year's Departmental Plan (dashed: the latest plan, for years not yet reported). Filled bar: actual.
Show the numbers
Fiscal yearPlannedActual
2018-19229252
2019-20276238
2020-21346282
2021-22321287
2022-23282467
2023-24290322
2024-25308413
2025-26393—
2026-27488—
2027-28489*—
2028-29485*—

Planned spending, plan by plan

Each row is one year's Departmental Plan and its forecast for the next three fiscal years; read a column down to see how the forecast for one year changed. The last row is what was actually spent. Click an amount for its source. Biggest changes in federal spending plans

Actual spending is from Departmental Results Reports and the Public Accounts, as published in GC InfoBase. FTEs are full-time equivalents.