Data Centre Information Technology Operations

Program code
BWD10 (SHARE)
Core responsibility
Data Centres
In Departmental Plans
2020-21 – 2020-21 · Appeared and later dropped

What it does

Data Centre Information Technology Operations is responsible for the coordination of data centres facilities equipment repairs and maintenance contracts plus the life cycle of all SSC data centre facilities, from overall strategy, initial planning and design, through to day-to-day operations.

It is also responsible for all data centre servers and appliances (ranging from mid-range to mainframe to supercomputers); platform services (application servers, web servers, and database software); operating systems; internal technical services; and storage, back up and archive. This not only includes day-to-day operations, but also overall strategy, initial planning, design life-cycle management, transformation, standardization and virtualization of all platforms to accommodate further IT demands of the Government of Canada.

Source: the department's Program Inventory, via GC InfoBase.

History and lineage

First appears in GC InfoBase's actual spending by program in 2020-21. The data does not record when a program was created; it may be older than its first appearance here, which is limited by the sources (program spending starts in 2010-11, Departmental Plans in 2018-19).

2020-212021-222022-232023-242024-252025-262026-272027-28Data Centre Information Technology Operations 2020-21: $691MData Centre Information Technology Operations 2021-22: $517MData Centre Information Technology Operations 2022-23: $519MData Centre Information Technology Operations 2021-22: $528MData Centre Information Technology Operations 2022-23: $688MData Centre Information Technology Operations 2023-24: $801MData Centre Information Technology Operations 2024-25: $745MData Centre Information Technology Operations 2025-26: $700MData Centre Information Technology Operations 2026-27: $644MData Centre Information Technology Operations 2027-28: $633MData Centre Information Technology O…Data Centre Information Technology Operations
Bars: spending by fiscal year (dark: actual; light: actual restated on the 2017-18 program structure; outlined: the latest plan's forecast; grey: related programs). Bands: each program in the lineage over the years it has data.
ProgramRelationYears with dataActual spending over those years
Data Centre Information Technology OperationsThis program2020-21 – 2022-23$691M
Data Centre Information Technology OperationsLater program (name match, high confidence)2021-22 – 2027-28$2.76B

Significant changes in scope and budget

Detected from the data: renames between plans, programs it appears to replace, merge with or split into (matched by name), year-over-year changes in spending of at least 25% and $5M, or in employees of at least 20% and 25 FTEs, linked budget measures, and results indicators added or dropped.

YearWhat changedSource
2021-22Appears to be replaced by Data Centre Information Technology OperationsCanada Spends name match across plans (an inference)
2021-22Planned spending $517M, against $691M in 2020-21 (−25%).Latest Departmental Plan

Success criteria

The program's indicators from its department's Departmental Results Framework: the target set in each year's plan, and the result reported the following year. Source: GC InfoBase.

Historical: targets against results

% Mainframe computers migrated from Legacy Data Centres to end-state Enterprise Data Centres
Expected result: Decreased complexity and increased efficiency to decrease footprint, reduce costs and increase ability to anticipate and respond to business needs
0%2020-21✗ not met

Bars: result reported. Dashed line: target.

Report yearTargetDueResultStatus
2020-21≥ 31%20210%
Migration of mainframes to enterprise DC's did not take place this past fiscal due to delays in a multi-stakeholder workload migration project and COVID restrictions.
Not met
% of time the bulk print services are available
Expected result: Efficient coordination of data centre equipment and data centre servers and appliances, platform services, operating systems, internal technical services and storage, back up and archive services.
100%2020-21✓ met

Bars: result reported. Dashed line: target.

Report yearTargetDueResultStatus
2020-21≥ 99.9%2021100%Met
% of time the mission-critical file services infrastructure is available
Expected result: Efficient coordination of data centre equipment and data centre servers and appliances, platform services, operating systems, internal technical services and storage, back up and archive services.
99.9%2020-21✓ met

Bars: result reported. Dashed line: target.

Report yearTargetDueResultStatus
2020-21≥ 99.5%202199.9%Met
% of time the mission-critical High Performance Computing (HPC) infrastructure is available
Expected result: Efficient coordination of data centre equipment and data centre servers and appliances, platform services, operating systems, internal technical services and storage, back up and archive services.
99.9%2020-21✓ met

Bars: result reported. Dashed line: target.

Report yearTargetDueResultStatus
2020-21≥ 98%202199.9%Met
% of time the mission-critical infrastructure for mid-range services is available
Expected result: Efficient coordination of data centre equipment and data centre servers and appliances, platform services, operating systems, internal technical services and storage, back up and archive services.
99.5%2020-21– no result

Bars: result reported. Dashed line: target.

Report yearTargetDueResultStatus
2020-21≥ 99.5%2021—
Mid-range services have been separated and their results are being reported on individually. There is no aggregate value reported anymore.
No result reported
% of time the mission-critical mainframe services infrastructure is available
Expected result: Efficient coordination of data centre equipment and data centre servers and appliances, platform services, operating systems, internal technical services and storage, back up and archive services.
100%2020-21✓ met

Bars: result reported. Dashed line: target.

Report yearTargetDueResultStatus
2020-21≥ 99.5%2021100%
The actual number is 99.997% but is given as 100.00% as all results are rounded to two decimal places.
Met
% of time the mission-critical storage infrastructure is available
Expected result: Efficient coordination of data centre equipment and data centre servers and appliances, platform services, operating systems, internal technical services and storage, back up and archive services.
100%2020-21✓ met

Bars: result reported. Dashed line: target.

Report yearTargetDueResultStatus
2020-21≥ 99.5%2021100%Met
Average Time to Restore Mainframe Services from Critical Incident
Expected result: Efficient coordination of data centre equipment and data centre servers and appliances, platform services, operating systems, internal technical services and storage, back up and archive services.
1622020-21✗ not met

Bars: result reported. Dashed line: target.

Report yearTargetDueResultStatus
2020-21≤ 602021162
Multiple mainframe outages happened during the course of 2020-21. These outages were twice or more than twice the length of downtime usually set as a target (60 min target) and led to the target not being met.
Not met

Current: the 2026-27 plan's targets

No indicators in the 2026-27 plan.

Future goals: targets due after 2026-27

No targets with a later due date.

Spending and employees: planned against actual

Spending

2020-21: $576M2020-21: $691M2020-212021-22: $517M2021-222022-23: $519M2022-23
Outlined bar: planned in that year's Departmental Plan (dashed: the latest plan, for years not yet reported). Filled bar: actual.
Show the numbers
Fiscal yearPlannedActual
2020-21$576M$691M
2021-22$517M*—
2022-23$519M*—

Employees (FTEs)

2020-21: 1,5232020-21: 1,6992020-212021-22: 1,5232021-222022-23: 1,5232022-23
Outlined bar: planned in that year's Departmental Plan (dashed: the latest plan, for years not yet reported). Filled bar: actual.
Show the numbers
Fiscal yearPlannedActual
2020-211,5231,699
2021-221,523*—
2022-231,523*—

Planned spending, plan by plan

Each row is one year's Departmental Plan and its forecast for the next three fiscal years; read a column down to see how the forecast for one year changed. The last row is what was actually spent. Click an amount for its source. Biggest changes in federal spending plans

Plan2020-212021-222022-23
2020-21 plan$575,641,893$517,092,490$519,205,059
Actual$690,695,952

Actual spending is from Departmental Results Reports and the Public Accounts, as published in GC InfoBase. FTEs are full-time equivalents.