Program directory · Shared Services Canada

Data Centre Information Technology Operations

Program code
BYE03 (SHARE)
Core responsibility
Common Government of Canada Information Technology (IT) Operations
In Departmental Plans
2021-22 – 2025-26 · Appeared and later dropped

What it does

Data Centre Service Branch (DCSB) is responsible for the development of plans, designs and operations of data centre services for the Government of Canada IT infrastructure. DCSB will provide full lifecycle management (strategy, plan, build, test, deploy, operate, and decommission) of its service offerings. DCSB key objectives include consolidating, standardizing and streamlining Government of Canada operations and database computing (data centre) services which support customer organizations’ delivery of programs and services to Canadians. DCSB functions include the end-to-end management of physical complexes; the establishment of computing environments for customer organizations and for SSC’s internal needs across all computing platforms; and the provision of technical support and certification for day-to-day operations, production applications and database computing environments.

Source: the department's Program Inventory, via GC InfoBase.

History and lineage

First appears in GC InfoBase's actual spending by program in 2021-22. The data does not record when a program was created; it may be older than its first appearance here, which is limited by the sources (program spending starts in 2010-11, Departmental Plans in 2018-19).

2020-212021-222022-232023-242024-252025-262026-272027-28Data Centre Information Technology Operations 2020-21: $691MData Centre Information Technology Operations 2021-22: $517MData Centre Information Technology Operations 2022-23: $519MData Centre Information Technology Operations 2021-22: $528MData Centre Information Technology Operations 2022-23: $688MData Centre Information Technology Operations 2023-24: $801MData Centre Information Technology Operations 2024-25: $745MData Centre Information Technology Operations 2025-26: $700MData Centre Information Technology Operations 2026-27: $644MData Centre Information Technology Operations 2027-28: $633MData Centre Information Technology O…Data Centre Information Technology Operations
Bars: spending by fiscal year (dark: actual; light: actual restated on the 2017-18 program structure; outlined: the latest plan's forecast; grey: related programs). Bands: each program in the lineage over the years it has data.
ProgramRelationYears with dataActual spending over those years
Data Centre Information Technology OperationsEarlier program (name match, high confidence)2020-21 – 2022-23$691M
Data Centre Information Technology OperationsThis program2021-22 – 2027-28$2.76B

Significant changes in scope and budget

Detected from the data: renames between plans, programs it appears to replace, merge with or split into (matched by name), year-over-year changes in spending of at least 25% and $5M, or in employees of at least 20% and 25 FTEs, linked budget measures, and results indicators added or dropped.

YearWhat changedSource
2021-22Appears to replace Data Centre Information Technology OperationsCanada Spends name match across plans (an inference)
2022-23Spending $688M, against $528M in 2021-22 (+30%).Actual spending (GC InfoBase)
2023-24Indicators dropped: % of time the bulk print services are availableDepartmental Results Framework (GC InfoBase)

Success criteria

The program's indicators from its department's Departmental Results Framework: the target set in each year's plan, and the result reported the following year. Source: GC InfoBase.

Historical: targets against results

% of Mainframe computers migrated from Legacy Data Centres to end-state Enterprise Data Centres
Expected result: Data Centre services are modern
0%2021-22✗ not met31%2022-23– no result31%2023-24– no result31%2024-25– no result

Bars: result reported. Dashed line: target.

Report yearTargetDueResultStatus
2021-22≥ 31%20220%
Canada Border Services Agency and Canada Revenue Agency mainframes are scheduled to be migrated in 2022-23. Migration of mainframes to enterprise Data Centres did not take place due to delays in a multi-stakeholder workload migration project.
Not met
2022-23≥ 31%2023—
Migration was completed prior to this fiscal year and this indicator will be removed in the future.
No result reported
2023-24≥ 31%2024—
Migration was completed prior to this fiscal year and this indicator will be removed in the future.
No result reported
2024-25≥ 31%2025—
Migration was completed prior to this fiscal year and this indicator will be removed in the future.
No result reported
% of time the mission-critical file services infrastructure is available
Expected result: Data Centre services are available
100%2021-22✓ met100%2022-23✓ met100%2023-24✓ met100%2024-25✓ met

Bars: result reported. Dashed line: target.

Report yearTargetDueResultStatus
2021-22≥ 99.5%2022100%Met
2022-23≥ 99.5%2023100%Met
2023-24≥ 99.5%2024100%Met
2024-25≥ 99.5%2025100%Met
% of time the mission-critical High Performance Computing (HPC) infrastructure is available
Expected result: Data Centre services are available
99.9%2021-22✓ met99.9%2022-23✓ met99.9%2023-24✓ met100%2024-25✓ met

Bars: result reported. Dashed line: target.

Report yearTargetDueResultStatus
2021-22≥ 98%202299.9%Met
2022-23≥ 98%202399.9%Met
2023-24≥ 98%202499.9%Met
2024-25≥ 98%2025100%Met
% of time the mission-critical Mainframe Services infrastructure is available
Expected result: Data Centre services are available
100%2021-22✓ met100%2022-23✓ met100%2023-24✓ met99.9%2024-25✓ met

Bars: result reported. Dashed line: target.

Report yearTargetDueResultStatus
2021-22≥ 99.5%2022100%Met
2022-23≥ 99.5%2023100%Met
2023-24≥ 99.5%2024100%Met
2024-25≥ 99.5%202599.9%Met
% of time the mission-critical storage infrastructure is available
Expected result: Data Centre services are available
100%2021-22✓ met100%2022-23✓ met100%2023-24✓ met99.9%2024-25✓ met

Bars: result reported. Dashed line: target.

Report yearTargetDueResultStatus
2021-22≥ 99.5%2022100%Met
2022-23≥ 99.5%2023100%Met
2023-24≥ 99.5%2024100%Met
2024-25≥ 99.5%202599.9%Met
Average Time to Restore Mainframe Services from Critical Incident
Expected result: Data Centre services are well-managed
242.882021-22✗ not met602022-23– no result6572023-24✗ not met572024-25✓ met

Bars: result reported. Dashed line: target.

Report yearTargetDueResultStatus
2021-22≤ 602022242.88
Multiple mainframe outages happened during the course of 2021-22. These outages were twice or more than twice the length of downtime usually set as a target (60 min target) and led to the target not being met.
Not met
2022-23≤ 602023—
As there were no critical incidents affecting Mainframe services this year, result is n/a for 2022-23.
No result reported
2023-24≤ 602024657
The target was missed due to an upgrade performed by the original manufacturer of the equipment which caused an error. The higher than expected restore time is the result of the time to engage the vendor, diagnose the issue, and develop the right strategy to restore services while preventing any loss of data.
Not met
2024-25≤ 60202557Met
Customer satisfaction with Data Centre services
Expected result: Data Centre services are well-managed
3.852021-22✓ met3.952022-23✓ met3.812023-24✓ met3.722024-25✓ met

Bars: result reported. Dashed line: target.

Report yearTargetDueResultStatus
2021-223.6 – 520223.85Met
2022-233.6 – 520233.95Met
2023-243.6 – 520243.81Met
2024-253.6 – 520253.72Met
% of time the bulk print services are available
Expected result: Data Centre services are available
0%2021-22✗ not met99.9%2022-23– no result

Bars: result reported. Dashed line: target.

Report yearTargetDueResultStatus
2021-22≥ 99.9%20220%
As of April 1 2021, Shared Services Canada (Mainframe Operations Management) has transferred Bulk Print and Insertion Services to Public Services and Procurement Canada and will not be reporting further.
Not met
2022-23≥ 99.9%2023—
Bulk Print and Insertion Services were transferred to PSPC in 2021-22. SSC will no longer be reporting on this and this indicator will be removed in the future.
No result reported

Current: the 2026-27 plan's targets

No indicators in the 2026-27 plan.

Future goals: targets due after 2026-27

No targets with a later due date.

Spending and employees: planned against actual

Spending

2021-22: $589M2021-22: $528M2021-222022-23: $724M2022-23: $688M2022-232023-24: $675M2023-24: $801M2023-242024-25: $752M2024-25: $745M2024-252025-26: $700M2025-262026-27: $644M2026-272027-28: $633M2027-28
Outlined bar: planned in that year's Departmental Plan (dashed: the latest plan, for years not yet reported). Filled bar: actual.
Show the numbers
Fiscal yearPlannedActual
2021-22$589M$528M
2022-23$724M$688M
2023-24$675M$801M
2024-25$752M$745M
2025-26$700M—
2026-27$644M*—
2027-28$633M*—

Employees (FTEs)

2021-22: 1,5272021-22: 1,8622021-222022-23: 1,7622022-23: 1,9822022-232023-24: 1,9842023-24: 2,1242023-242024-25: 2,2222024-25: 2,1192024-252025-26: 2,2012025-262026-27: 2,2012026-272027-28: 2,1982027-28
Outlined bar: planned in that year's Departmental Plan (dashed: the latest plan, for years not yet reported). Filled bar: actual.
Show the numbers
Fiscal yearPlannedActual
2021-221,5271,862
2022-231,7621,982
2023-241,9842,124
2024-252,2222,119
2025-262,201—
2026-272,201*—
2027-282,198*—

Planned spending, plan by plan

Each row is one year's Departmental Plan and its forecast for the next three fiscal years; read a column down to see how the forecast for one year changed. The last row is what was actually spent. Click an amount for its source. Biggest changes in federal spending plans

Actual spending is from Departmental Results Reports and the Public Accounts, as published in GC InfoBase. FTEs are full-time equivalents.